DuPont Schedule

The DuPont schedule is a 28-day rotation of 12-hour shifts for four crews: 4 nights, 3 off, 3 days, 1 off, 3 nights, 3 off, 4 days, then 7 days off. It averages 42 hours a week. See the full cycle below and print a calendar with every date filled in.

At a glance

Cycle length
28 days
Shift length
12 hours
Shifts per cycle
14
Average per week
42 hours
Crews
4
Longest run of shifts
4 in a row

Make your DuPont calendar

The calendar below opens with the DuPont rotation and today as day 1. Pick your crew, set the date one of your shifts falls on, add other people if you like, then print or download the PDF. Changes are saved in this browser.

Calendar

Up to 366 days. Changing these dates never resets the rotation.

Time format

People and rotations

Shift types
  • 07:00–19:00 · 12 h
  • 19:00–07:00 +1 · 12 h
Rotation

1–56 days. It doesn't have to be 7 or 28.

Pick a shift, then click days in the cycle to fill them

Line up with a known date

If you know a date when crew A started day 1, enter it above as the known date and pick your crew. Crew letters vary by employer, so check one known shift.

One-day changes

No one-day changes yet. Click a day in the preview to swap or cancel a shift.

Print and export

Layout
Paper
Orientation
Week starts on

Holidays are labels only. They never skip or shift the rotation.

Import into Google Calendar, Apple Calendar or Outlook. It's a one-time copy: importing again later may create duplicates.

Loading your saved plan…

One full DuPont cycle, crew by crew

Day 1 is the first day of crew A's cycle. Each crew follows the same pattern, started on a different day.

  • D Day shift
  • N Night shift
  • –No new shift
Week 1Week 2Week 3Week 4
Day 12345678910111213141516171819202122232425262728
Crew A N N N N – – – D D D – N N N – – – D D D D – – – – – – –
Crew B – – – – – – – N N N N – – – D D D – N N N – – – D D D D
Crew C – – – D D D D – – – – – – – N N N N – – – D D D – N N N
Crew D D D D – N N N – – – D D D D – – – – – – – N N N N – – –

How the DuPont schedule works

Each crew works the same 28-day sequence: 4 night shifts, 3 days off, 3 day shifts, 1 day off, 3 night shifts, 3 days off, 4 day shifts, then 7 days off. That is 14 shifts of 12 hours, or 168 hours, in four weeks.

Four crews start the cycle a week apart, so on every day one crew works the day shift and another works the night shift. The rotation is named after the DuPont chemical company, where it was used in plants that run around the clock.

The week off is the main draw. The price is the hardest stretch of the cycle: a run of four nights, and later a block of three nights followed by four days with only three days off in between.

Pros

  • Seven days off in a row every four weeks.
  • Average of 42 hours a week with only 14 shifts in 28 days.
  • Every crew shares days, nights and weekends equally.

Cons

  • Up to 4 12-hour shifts in a row, including four nights.
  • Only one day off between the day block and the next night block.
  • Switching between days and nights within each cycle is hard on sleep.

DuPont Schedule FAQ

How does the DuPont schedule work?

Each crew works 4 nights, has 3 days off, works 3 days, has 1 day off, works 3 nights, has 3 days off, works 4 days, then has 7 days off. The 28-day cycle then repeats, with four crews starting a week apart.

How many hours is a DuPont schedule?

42 hours a week on average: 14 shifts of 12 hours over 28 days, 168 hours in total. Individual weeks are longer or shorter than the average.

How many days off do you get on a DuPont schedule?

14 days off in every 28-day cycle, including one stretch of 7 days off in a row.