2-2-3 Schedule

A 2-2-3 schedule repeats every two weeks: work 2 days, off 2, work 3, off 2, work 2, off 3. Shifts are 12 hours, so it averages 42 hours a week. In the rotating version shown here, crews switch between days and nights every two weeks, so the full cycle is 28 days. See every crew's rotation below and print your own calendar with every date filled in.

At a glance

Cycle length
28 days
Shift length
12 hours
Shifts per cycle
14
Average per week
42 hours
Crews
4
Longest run of shifts
3 in a row

Make your 2-2-3 calendar

The calendar below opens with the 2-2-3 rotation and today as day 1. Pick your crew, set the date one of your shifts falls on, add other people if you like, then print or download the PDF. Changes are saved in this browser.

Calendar

Up to 366 days. Changing these dates never resets the rotation.

Time format

People and rotations

Shift types
  • 07:00–19:00 · 12 h
  • 19:00–07:00 +1 · 12 h
Rotation

1–56 days. It doesn't have to be 7 or 28.

Pick a shift, then click days in the cycle to fill them

Line up with a known date

If you know a date when crew A started day 1, enter it above as the known date and pick your crew. Crew letters vary by employer, so check one known shift.

One-day changes

No one-day changes yet. Click a day in the preview to swap or cancel a shift.

Print and export

Layout
Paper
Orientation
Week starts on

Holidays are labels only. They never skip or shift the rotation.

Import into Google Calendar, Apple Calendar or Outlook. It's a one-time copy: importing again later may create duplicates.

Loading your saved plan…

One full 2-2-3 cycle, crew by crew

Day 1 is the first day of crew A's cycle. Each crew follows the same pattern, started on a different day.

  • D Day shift
  • N Night shift
  • –No new shift
Week 1Week 2Week 3Week 4
Day 12345678910111213141516171819202122232425262728
Crew A D D – – D D D – – D D – – – N N – – N N N – – N N – – –
Crew B – – N N – – – D D – – D D D – – D D – – – N N – – N N N
Crew C N N – – N N N – – N N – – – D D – – D D D – – D D – – –
Crew D – – D D – – – N N – – N N N – – N N – – – D D – – D D D

How the 2-2-3 schedule works

The name describes the first week of the pattern: two days on, two days off, three days on. The second week is the reverse: two days off, two days on, three days off. Over 14 days you work 7 shifts of 12 hours, 84 hours in total.

To staff a job around the clock, four crews share the work. Two crews cover days and two cover nights, and each pair splits the calendar so that one crew is always on. The version on this page rotates: each crew works two weeks of day shifts and then two weeks of night shifts, so a full cycle is 28 days.

Some workplaces keep crews on fixed days or fixed nights instead of rotating. That fixed version is often called the Pitman schedule, and some call the rotating version a Panama schedule. The days on and off are the same in all three; only the change between days and nights differs.

Pros

  • Never more than 3 shifts in a row.
  • If the three-day blocks fall on Friday to Sunday, every other weekend is a three-day weekend.
  • Fewer trips to work: 7 shifts every two weeks instead of 10.

Cons

  • 12-hour shifts are tiring, and the days you work change from week to week.
  • In the rotating version, switching from days to nights every two weeks is hard on sleep.
  • You work every other weekend, and the 84 hours fall unevenly across the two weeks, which can matter for overtime.

2-2-3 Schedule FAQ

How many hours a week is a 2-2-3 schedule?

42 hours on average. You work 7 shifts of 12 hours every two weeks, which is 84 hours. Depending on where your pay week starts, that can be split as a 36-hour week and a 48-hour week, or another uneven split.

What is the difference between a 2-2-3 and a Pitman schedule?

The days on and off are the same. The name Pitman is usually used for the version where crews stay on fixed day or night shifts; a rotating 2-2-3 moves each crew between days and nights, here every two weeks.

How many crews does a 2-2-3 schedule need?

Four crews to cover 24 hours a day, every day: two on 12-hour day shifts and two on 12-hour night shifts. If you only run one 12-hour shift a day, two crews are enough.

Can I use a 2-2-3 calendar for custody?

A 2-2-3 parenting schedule uses the same pattern of days. You can set it up here with one person per parent and an all-day shift type, then print it. This page describes the work rotation.

Print your 2-2-3 calendar

Free, no account, no watermark.