2-2-3 Schedule
Work 2, off 2, work 3 on 12-hour shifts. Four crews, 42 hours a week on average.
A 4 on 4 off schedule is four 12-hour shifts followed by four days off, repeated every 8 days. It averages 42 hours a week, and because the cycle is 8 days, your days off move one day later each week. Print a calendar to see exactly which days you work.
The calendar below opens with the 4 on 4 off rotation and today as day 1. Pick your crew, set the date one of your shifts falls on, add other people if you like, then print or download the PDF. Changes are saved in this browser.
Up to 366 days. Changing these dates never resets the rotation.
No one-day changes yet. Click a day in the preview to swap or cancel a shift.
Holidays are labels only. They never skip or shift the rotation.
Import into Google Calendar, Apple Calendar or Outlook. It's a one-time copy: importing again later may create duplicates.
Loading your saved plan…
Day 1 is the first day of crew A's cycle. Each crew follows the same pattern, started on a different day.
| Day | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
|---|---|---|---|---|---|---|---|---|
| Crew A | D | D | D | D | – | – | – | – |
| Crew B | – | – | – | – | D | D | D | D |
You work four shifts of 12 hours, then have four days off, and the cycle repeats. Two crews alternate, so one crew is always on duty for that shift. For 24-hour coverage, two more crews do the same on nights, or each crew does two days and two nights in its four shifts.
Because 8 days is not a whole number of weeks, your working days move: if you start on a Monday this cycle, you start on a Tuesday next cycle. That is why a printed calendar helps more here than with weekly rotations.
Over a year you work about 182 shifts, the same number of hours as a 42-hour week.
42 hours on average: 4 shifts of 12 hours every 8 days. Individual weeks vary between 36 and 48 hours.
About 182 or 183, half the days of the year, because the cycle is exactly half on and half off.
The cycle is 8 days long, one day longer than a week, so each new cycle starts one weekday later than the last.
Yes. Add a night shift type in the tool and set the four working days to two days and two nights, or whatever your site uses.